Rough Inspection
The important principle to remember is that all work must be inspected prior to concealment. It is possible that all of the construction trades are coordinated enough so that all the rough-in inspections can be accomplished during one inspection. However, it is unlikely that the insulation inspection can be done at the same time because the insulation normally conceals the other work. Also, the rough framing inspection is best done after the electrical and heating work is done so that notching and boring can be checked.
Occasionally, a contractor will not properly call for an inspection so that the inspector does not have the opportunity to verify compliance prior to concealment of some work. Possible options that the municipality may consider are:
Selection of the option(s) is at the discretion of the municipality and should be done in consultation with the municipal legal counsel.